A new study available will help subcontractors battle the looming threat of compensation losses from obstacles on the job site.
 |
| Framing
inspection failure due to improper MEP installations. |
|
Inspired
by similar studies of the specialty trades (notably mechanics and
electricians), the study examines the impacts to labor productivity in the wall
and ceiling industry. The study looks into the impact of 38 variables on 226
separate projects. The published data finds that unexpected labor congestion,
fragmentation, overtime and added shift work negatively impacted labor
productivity.
Because labor productivity is the single greatest variable affecting the
construction contractor’s cost of production and profitability, the findings of
the study can help contractors get compensated for losses due to change orders
and other factors out of their control.
“Why it [the study] got started is wall and ceiling contractors were having
challenges with the general contractor and owner on getting paid for extra or
loss of productivity time that they had to do,” says Bob Drury, executive
director of the NWCB.
Drury says in order to make a labor impact study valid, an independent source
has to do this research.
“In a court of law, it has to be an academic document. In other words, we hired
a consultant and we hired Portland State University,” says Drury.
 |
| MEP
installation not within the partition cavity, preventing scheduled installation
of drywall. |
|
HOW
IT BEGAN
When asked why the study was written, one of the study’s writers, Gerald H.
Williams, Jr., PhD, P.E. of Construction Research Inc., out of Portland, says
drywall activities make up approximately 10 percent of construction costs, and
between 60 to 70 percent of metal framing, drywall, tape and finish work is
direct application labor.
“This means that labor productivity normally has the greatest potential impact
on the drywall contractor’s cost of production. Granted, the run-up in steel
prices in 2004 and 2005 also had a great impact but that was an unprecedented
event,” says Williams. There have been no previous studies of labor
productivity or factors impacting labor productivity in the metal stud framing,
drywall, tape and finishing trades, he says.
This study was done to research what factors actually impact labor productivity
in the framing and drywall trades and to what extent. The findings provide the
link between an event or condition on a project (such as crowding or work
fragmentation) and its negative impact on labor productivity, Williams says.
In a project-management setting, a party that is considering whether or not to
make changes to an as-bid construction schedule that would affect metal-stud
framing and the installation and finishing of drywall, would be well served by
reading the study due to the consequences of such a change, says Alan
Bornstein, an attorney with Jameson, Babbitt, Stites, & Lombard, P.L.L.C.
in Seattle.
“The study describes the interrelationship of metal-stud framing and the
installation and finishing of gypsum wall board with other trades in a typical
construction sequence on a commercial project,” he says. “When that typical
construction sequence is altered, it has a ripple effect not only upon the work
of the drywall contractor, but also on the other trades whose work is
interrelated, such as the mechanical, electrical, and plumbing trades. The
study describes how that ripple effect makes labor—typically the largest cost
component on any construction project—inefficient and therefore, more expensive
as a project cost.”
In a claims setting, where the drywall contractor believes that he has suffered
a labor-productivity loss, the drywall contractor now has access to a study to
help support his particular claim, Bornstein continues.
“The study is no substitute for proof,” he says. Everyone involved in the
production of the study confirm that it is helpful only where the drywall
contractor can establish that another party, such as the GC or other trades,
caused obstacles in the construction schedule and that the labor inefficiencies
were not of its own making.
Jim Dunham, vice president of field operations with Vanderlip & Co. Inc.,
of Redmond, Wash., and also sits on the NWCB’s Board of Directors as president,
says: “I think the main factors in loss of productivity are any interruption of
flow of work: to start an area of work, stop, remobilize, start-again (a new
crew will have a certain learning curve to get a flow going); trying to work in
the same area as other trades always leads to conflicts and lack of
productivity; adding more workers to an area than the area can handle to try
and catch up on a slipping schedule.”
 |
| Out
of sequence HVAC installation, preventing access for drywall installation. |
|
PUT
TO USE
In theory, the study sounds great. But does it work for the contractor, who has
to count on the fact that the GC or owner will actually read the manual?
“In theory, this study will support the subcontractors’ claims that being
forced into these situations that there is merit to the fact that they are
losing productivity, time and money,” says Dunham.
Since the study has become available, he’s noticed that general contractors and
owners are more willing to discuss possible production losses as they occur.
“Recently we had a project that the door frames had not arrived on the project
and were not installed,” Dunham says. “The contractor wanted us to frame that
area because the schedule showed that area to have been already framed. We were
able to convince the general that even though there would be little or no added
footage to that area, coming back to complete the framing at those door jamb
areas would not be completed for the same hours or production we bid the
project. We were given a change order to cover our lost hours.”
According to James Kahler, vice president of Northwest Partitions Inc., of
Kent, Wash., the study’s power is that owners and contractors listen because it
is a published statistical study that incorporates a large sampling of projects
(226 polled) from several wall and ceiling contractors.
But has the study had a direct impact working for its subcontractors? Yes,
absolutely says Kahler.
“We were involved in a project that would not allow the completion date to be
pushed out even though the project required some redesign early on,” he says.
“This owner-delay required the project schedule be compressed. The compressed
schedule necessitated overtime, out-of-sequence work, trade stacking, ramp-ups
and ramp-downs and diluted supervision for us. The owner originally proposed
only paying the overtime premium. With the assistance of the study, Northwest
Partitions was able to prove entitlement, avoid litigation, and resolve the
matter amicably, which resulted in a change order for us in excess of $85,000.
It helped that we had our documentation in place early on and were continually
communicating the potential negative labor impacts to the GC and owner. The
study was the icing on the cake.”
According to Drury, the study is not just relevant to subcontractors out west
but is a tool that is available from the NWCB for contractors throughout North America.
“This document is a tool for the contractor and his legal team/consultants to
use so they can show loss of productivity—i.e. money,” says Drury.
Williams double-downs on Drury’s sentiment: “One thing I think that needs to be
recognized is that drywall contractors, particularly on larger projects, need
to be aware of the factors we studied, understand their contractual notice
requirements, and keep good productivity records. In the end, the study proves
causation but it can only be used as a broad guide to the amount of impact.
Contractors have to keep good job-cost records so that an analyst can prove the
magnitude of impact.”
The study is available from the NWCB. Visit
www.nwcb.org. W&C