In
late December, most of us are busy planning for the upcoming holidays, thinking
about eating lots of fattening foods, and looking forward to merry-making with
family and friends. On December 23, 2008, however, one person was not enjoying
such pleasant thoughts. Instead, Larry Spielvogel, PE, was finishing up a
letter of appeal to USGBC President Rick Fedrizzi contesting a LEED Gold Certification
that had been recently awarded to the Northland
Pines High
School in Eagle River,
Wis. The letter of appeal is an
exhaustive, 125-page tome documenting many violations of the LEED rating system
during design and construction of the $28.5 million high school. Spielvogel and
another engineer, both members of the Northland Pines High School Building
Committee, wrote the letter on behalf of the entire Building Committee as well
as the taxpayers of Vilas County Wisconsin.
On April 27, after reviewing the appellant’s documents and investigating the
allegations made, the USGBC denied the appeal with the following
statement:
“After extensive review, USGBC and its consultants have no reason to believe
that the project failed to meet all of the LEED prerequisites and credits that
it has attempted. Thus, USGBC will not act to revoke certification or disallow
any prerequisites or credits. Northland
Pines High
School will retain the 40 points awarded to the
project in its original review. The project remains certified at the Gold
level.”
And with that, all parties should be satisfied; satisfied that the appeal
process was implemented fairly, that it worked, and that the building is worthy
of its LEED Gold status. If only that were the case!
The Greening of Northland Pines High School
In 2004, voters approved $28.5 million in bonds to finance the design and
construction of the Northland
Pines High
School. Spielvogel served on the Building
Committee for the new school along with other professionals with specific
talents and experience in design and construction of large buildings. Each was
dedicated to the proposition of creating the most efficient structure
possible.
As the design developed, building committee members began to question whether
the facility would meet the necessary requirements for LEED certification when
shortcomings in the design became apparent. The board hired two consulting
engineers to review the design, and both concluded that the facility as
designed would not meet some of the prerequisites for LEED certification.
According to Spielvogel, this information was ignored by the design team and
work on the high school proceeded without changes necessary to ensure LEED
certification would be obtained.
But LEED certification was obtained, and not the LEED Silver rating originally
targeted, but LEED Gold. In disbelief of this, the appeal was filed challenging
the award of the LEED Certification. It took the USGBC 16 months to conclude
that the appellant’s allegations were unfounded, and that the building would
retain its LEED Gold certification.
According to Spielvogel: “They based this on reports from two more consulting
engineers who said that the building did not meet the prerequisites but
concluded that ‘pretty close’ is close enough. When the appellants’ engineers
asked for the back up data to the USGBC reports, they were told that they were
pretty busy and would address that request when they had time. Time has passed
and the requested materials have not been forthcoming. Why?"
“On behalf of the taxpayers of Vilas County who would like to know with
certainty whether they got what they paid for or not, we ask the engineering
community to look at this file and tell us, did we miss something here? How can
it be all right to certify a building that doesn’t fully comply with the rules
set forth by the body that is doing the certifications?”
LEED Certification Appeal: A Deeply Flawed Process
The Northland Pines appeal includes, in one of the appendices, a document
titled U.S. Green Building Council Process for Appeal of LEED Certification,
which outlines the appeal process in flowchart fashion. If a Technical Review
is warranted, based on conclusions of an initial USGBC review, independent
consultants are to be engaged by the USGBC to assist in further review. The
document states that “consultants will have no conflict of interest with either
LEED project team or appellant.” What about conflict of interest with the
USGBC? That is seemingly addressed in a separate USGBC document titled “GBCI
LEED Certification Policy Manual” under Certification Challenge Policy, which
was created after the initiation of this appeal. The policy
states:
No staff or technical consultant may: (a) review any matter in which his or her
impartiality might reasonably be questioned, or (b) review any matter which
presents an actual, apparent or potential conflict of
interest.
It’s a good thing that this policy did not exist at the time of this appeal,
because the USGBC would not have met the requirement in hiring two engineers to
assist with the Technical Review of the Northland Pines appeal. One of the
engineers sits on at least one USGBC Technical Advisory Committee and also
teaches classes for the USGBC. His Web site lists the USGBC as a client under
Teaching Services. The other engineer, according to his company’s Web site, has
been a “featured lecturer and presenter at USGBC Salons” as well as having
spearheaded commissioning guidelines for LEED-NC Version 2.2, and served on the
New York City Chapter Board of Directors of the U.S. Green Building Council.
It comes as no great shock that the reviewers hired by the USGBC are generally
dismissive of the allegations made in the appeal, given the clear conflict of
interest that exists. What is shocking is how clearly they conclude that the
building does not, in fact, meet the prerequisite requirements for LEED
certification. Even more shocking is that the USGBC completely ignores this in
its declaration that it has “no reason to believe that the project failed to
meet all of the LEED prerequisites and credits …”
Here is a sampling of the consultant’s conclusions that support the appellant’s
claims:
There were several violations of Standard 62.1 and Standard 90.1 requirements
in the design as originally documented. As such, the original design did not
meet Indoor Environmental Quality (EQ) Prerequisite 1 and Energy and Atmosphere
(EA) Prerequisite 2 of LEED NC version 2.1.
There appears to be a violation of the reheat limitation: heating airflow set
points on VAV box schedules on H1.2 are significantly above the limitations
prescribed by Section 6.3.2.1 exception (a).
The calculation methodology [under 4.1 Ventilation Rate Procedure] did not
strictly meet Standard 62.1.
Complainants point out, correctly, that none of the VAV air handling units
includes airflow measuring devices on the outdoor air intakes. CO² sensors are
provided in the return air of most units, with controls to increase outdoor air
minimum damper position when CO² rises above 800 ppm. This helps compensate for
the lack of airflow measurement and control, but it does not meet the Standard
since there is no way that it can maintain the “building component” of the
ventilation rate.
It is not readily apparent if the systems as designed meet this section [5.10
Dehumidification Systems]. The VAV systems should meet it inherently since
supply air temperatures are generally always low enough to dehumidify in cold
weather. However, the constant volume units may not in some weather. This is a
possible technical violation.
It is not clear that commissioning requirements were included in documentation
[as required for LEED 2.1 NC EA Prerequisite 1].
The USGBC failed to follow its Process for Appeal upon the finding by its
consultants that violations existed. The next step outlined in the Process for
Appeal, after it is determined that a prerequisite is not met, requires removal
of the LEED certification plaque, or De-Certification.
Conclusion
The Northland Pines appeal, and subsequent denial of the appeal by the USGBC,
has not resulted in a lawsuit—yet. But it is probably just a matter of time
before an appeal is made on another LEED certification and litigation (or
“LEEDigation” as it has been termed in one popular green building law blog)
ensues. Spielvogel and the rest of the appellants declined to pursue legal
action against the USGBC, but instead wrote a paper titled USGBC and LEED
Credibility Destroyed which summarizes their entire ordeal. The paper concludes
that:
“The USGBC decision to reject this appeal is going to matter. Like it or not,
USGBC set a dangerous precedent by turning a blind eye to a deliberately
deficient submission. They sent a message to applicants that it is OK to make
unsupported claims in their Certification submissions, and that USGBC will not
act against them even when deficiencies are disclosed. How many other projects
like this are out there? That should be a matter of grave concern to potential
applicants considering the time and expense of getting their facilities LEED
Certified.”
Green building and construction law attorneys have been following the saga of
the Northland Pines appeal with great interest. Their blogspots are rife with
commentary, advice and speculation. For an excellent summary of all of this
Internet activity and some very provocative discussion points, I recommend a
recent post titled Challenges to LEED Certifications: Standing, Procedure,
Wiggle Room and Money at Virginia Real Estate, Land Use & Construction Law
Blog (ht.ly/22J2r).
ChrisDixon Chris Dixon is a registered architect, Certified
Construction Specifier, and LEED AP. He serves on GBI’s Green Globes Technical
Committee and is a former USGBC Materials and Resources Technical Advisory
Group member.
|
Did you enjoy this article? Click here to subscribe to the magazine.