Corner Shop
Corners are furred using rigid foam insulation along with the flanged furring
channels. The approach to corners using rigid foam, sized at 2 inches by 4
inches, was developed the hard way.
“We tried to use spray foam but it simply didn’t work as the expansion of the
foam wreaked havoc,” says Ken Keranen, general manager of Superior Polymer
Products.
Another local contractor and block producer Dan Lorenzetti, of Superior Block,
suggested using 2 inch by 4 inch rigid foam to fill the corner. The idea worked
so well it was immediately adopted. Now, all inside and outside corners are
furred-out using the technique.
In place of a bottom plate, 2 inch by 2 inch rips of rigid foam are glued
directly to the floor leaving a 1½ inch gap between the base of the wall and
the foam. This approach allows the closed cell foam to act as a radon block at
the control joint and when it continues up into the band joist it creates a 100
percent airtight basement.
“If you are using bat or blown-in insulation, we’d recommend using a 3½ inch
wide rip of foam at the base,” says Keranen.
The top plate—if used—is a 2-inch by 2-inch or 2-inch by 4-inch pine rip
attached to the floor joists.
“Because we want to integrate our insulation with the band joist, we typically
eliminate the top plate, but in the end we do what the customer wants,” says
Keranen.
Furring Openings
Another feature of the system is the method of furring openings. Around windows
and doors, the frames are made using the flanged furring channel with the
flange ripped off on a table saw. Joints are made using L-brackets
fabricated on-site using off-cuts with the base cut off. These are attached
using 1/2-inch needle point screws. To complete the furring around the windows
and doors the flange is cut off the channels using a table saw, a 1/2-inch hole
is drilled in the face of the channels on 18 inch centers and the channel is
held in position while using a hammer drill to make the first 3/16-inch hole
for the concrete screw. After the first hole is drilled, the piece is attached
with a screw to hold position while drilling the balance of the holes. Once the
remaining holes are drilled the holding screw was removed, the piece is removed
to apply the adhesive and it is repositioned and made fast with screws in all
the previously drilled holes.
The installation time of the flanged furring channel for the 1,500 square foot
L shaped basement with two large windows and a door was three hours with two
installers.
Power tools used during the install included a table saw, chop saw, small
hammer drill, portable drill and a track nailer. Other tools included a level,
tape measure, caulking gun.
“Prior
to arriving at the job the guys prep by cutting all the corner and base foam at
the shop, it increases the speed of the install significantly and makes the
transport to the job much easier” says Keranen. He further explains that they
follow a standard sequence when arriving at a project: “The leader takes the
corner foam rips and immediately completes the corners while the helper is
unloading the rest of the tools and stocking the job. This simplifies the
layout work for the project as a tape is drawn out from the corners and the
marks are made on the wall, not the floor. Once the layout work is done the
lead man leaves the helper to attach the flanged furring channels to the wall
using a 7-foot level and the track nailer while the leader moves on to the
openings. Whoever finishes first takes the flooring foam rips and glues them in
place. This approach keeps the team moving at all times without being in each
others way.”