Walls & Ceilings logo
search
cart
facebook twitter linkedin youtube youtube Spotify Podcasts Apple Podcasts Spotify Podcasts Apple Podcasts
  • Sign In
  • Create Account
  • Sign Out
  • My Account
Walls & Ceilings logo
  • NEWS
  • TOPICS
    • Drywall
    • Stucco/EIFS
    • Ceilings
    • Steel Framing
    • Fireproofing
    • Interior Plaster
    • Building Envelope
    • Insulation
    • Technology
    • Interior
    • Exterior
    • Women In Construction
  • COLUMNS
    • Up Front
    • All Things Gypsum
    • Art & Craft of Plastering
    • Stucco Stop
    • Steel Deal
    • Industry Voices
  • PRODUCTS
    • Buzz Guide
  • EVENTS
    • Industry Events
    • Webinars
    • BUILD Expo
  • MEDIA
    • Videos
    • Podcasts
    • Photo Galleries
    • BUILD26 Videos
    • Take our Quiz!
    • Infographics
  • EXCLUSIVE
    • Newsletters
    • Top 50 Contractors
    • Contractor of the Year
    • State of the Industry
    • W&C Store
    • Market Research
    • CEUs
    • Sponsor Insights
    • Custom Content & Marketing Services
  • DIRECTORY
  • EMAGAZINE
    • eMagazine
    • Advertise
    • Archive Issues
  • SIGN UP!
ColumnsDrywallTechnology

ALL IN AGREEMENT

The Truth Behind Change Order Revenue

No Wiggle Room

By Pete Battisti
September 1, 2014

Is there a difference between original contract revenue and change order revenue? Or are you of the opinion that once a change order is approved it becomes original contract revenue? When subcontractors submit their monthly payment application, the subcontractor enters the original contract amount on one line and the amount of approved changes to date on another line, resulting in a “total revised” contract amount, which should match the total on the last change order received.

change order chart

In essence, the total revised contract amount may be viewed as one revenue “bucket,” when there are actually two revenue buckets. My goal in writing this article is to provide a convincing argument that change order revenue is different from original contract revenue, from an operational and accounting perspective. 

We can agree that change order revenue is generally the sum total of labor, material and equipment costs plus markup. However, when you dump these costs into the original contract amount bucket, the bucket becomes distorted. Consider for a moment the advantages of putting change order revenue in a separate bucket. A simple solution in separating the two buckets is to have an original contract bucket and a change order bucket. There are other ways to separate the buckets within one job cost depending upon your job costing system, and your change order polices.

Advantages

What are some of the advantages in separating original contract revenue from change order revenue? First and foremost, it gives you the ability to analyze each bucket to determine whether or not you’re making or losing money on the original contract revenue or change order revenue. For example, a $200,000 original contract plus $60,000 worth of change orders is a 30 percent increase in the original contract amount. At minimum, when you dump an additional 30 percent of revenue into the original contract value, you will most often see a positive impact to the job cost until your change order costs start hitting the job costs. This normally results in a temporary job cost distortion until all change order revenue and costs hit the job cost.

As you know, a project financial picture usually becomes clearer at roughly 50-75 percent complete for a variety of reasons. However, if a job continues to have a substantial amount of changes or if large changes are added at the 50-75 percent complete range, the financial picture is more difficult to evaluate. 

In addition to knowing quickly whether or not you’re making or losing money on either of the job costs, as well as not distorting the job cost, there are many other advantage in keeping the two buckets separated. For example:

  • Ability to analyze original estimate for accuracy, and to use that information to evaluate an estimator’s performance by project or at minimum annual review.
  • Ability to evaluate a project managers change order pricing methods, separately from his ability to manage the original contract value and to use information to evaluate performance in both areas.
  • Ability to better determine if changes are having a negative impact on original contract work.
  • In the event of a formal claim, a claims consultant will have a clear picture of “input and output,” related to original contract amount vs. change order “input and output.”
  • Keeps you in compliance with most contract language requiring subcontractors to account for costs associated with each change.
  • Ability to analyze whether or not you are capturing all change order costs including but not limited to the role and responsibility of a foreman in orchestrating a change.

Foreman’s Role in Orchestrating Changes

Let’s say for example that a $200,000 job, having a 30 percent increase or $60,000 in changes, may result in the foreman spending 70 percent of his time on original contract revenue and 30 percent of his time being spent on change order revenue. However, when a foreman’s change order time is dumped into the black hole of the original and change order revenue combined, you won’t know how much time he is exhausting on each individually.

In most cases, subcontractors underprice change orders for a variety of reasons. However, most think, (at the time) they are making a lot of money on change orders. The problem is they don’t have a mechanism in place to prove they are making money on individual changes separately from original contract work. Here is one example in one category as to why changes are often underpriced. I feel the following form tells the story best.

To set the stage, an estimator or project manager typically reviews a change and adds a certain number of foreman hours based on what he or she believes, it will take a foreman to complete a change. The problem is that foreman don’t just complete changes, there is actually a process involved in orchestrating a change from start to finish.

In reality there are a minimum of four phases in the change process. They consist of the planning-approval phase, construction phase, accounting phase and close out phase. There are a total of 20 cost considerations in the four phases, however the person pricing a change must keep in mind the complexity of the change as he or she applies time to each of the cost considerations.

For example, Section A item 2 identifies a foreman cost consideration as, “Time to Review and Understand Change.” Depending upon the complexity of the change a foreman will always spend time reviewing and understanding a particular change.

Section B item 3 identifies a foreman cost consideration as, “Time to Procure Labor,” possibly multiple times for a particular change. This involves scheduling/planning and always takes time.

Section C item 1, describes the foreman’s role in “Managing Time Cards” related to a particular change. Section D is simply the closeout phase of a change, which might include demobilization or other documentation, such as client verification.

Even though this form provides you with a systematic approach to identifying the amount of time a foreman will spend managing a change, some readers will automatically defer to adding roughly 10 percent of labor hours to the foreman labor category. Meaning, if a foreman costs $50 per hour, and a change is priced having 20 labor hours, adding two hours or $100 in foreman labor just isn’t enough.

However, getting back to the original point being, that unless you account for original contract revenue and change order revenue separately you won’t know if your charging enough foreman time.

Bucket of Changes

In a perfect world, wouldn’t it be nice if two entirely different teams did original contract work verses change order work on jobs having a substantial amount of changes? Put another way, what would be the biggest difference if one team was responsible for original contract work and the other was responsible for change order work?

The biggest difference would be in how each team ‘accounted’ for original contract costs verses change order ‘pricing and costs.’ In other words, if a team’s sole source of revenue and profit is based on how well they do on change order work, you can be sure change order work will be accurately accounted for and vice-versa.

However, in the real world of construction, making two separate teams accountable is unrealistic and a duplication in costs, or is it? It depends upon how a project manager prices each change and how he manages the original contract costs verses change order costs.

For example, if a $200,000 job was bid to achieve a 15 percent margin, and the $60,000 in changes were priced to achieve a 25 percent margin, the total margin, if both the original contract value and changes are lumped together along with costs, should leave an owner wondering why the job cost ends up showing a gross of profit of only 10-12 percent

Did the subcontractor lose 3-5 points on the original contract work or did he lose 10-20 points on the change order work? Was the original estimate accurate or were the change orders priced inaccurately? The only way to answer that question is to subtract the $60,000 in change order revenue and their associated costs from the job costs, which is nearly impossible to do accurately after the fact.

Consider for a moment having a $10,000,000 job with an additional $3,000,000 in change order work, again, roughly 30 percent of the original contract amount. As you begin to recognize $3,000,000 in revenue and the associated costs, your job cost will become distorted until you recognize all the revenue and all change order costs, which is usually towards the latter end of the job.

In doing so, your costs climb, which forces you to recognize more revenue, however, you won’t know how much money you’re making on the changes until all change order costs hit the job cost. In many cases, we call this the yo-yo effect. Executive calls project manager and says, “Hey, your job cost dropped two points-what’s going on?” The typical reply is, “We’re doing a lot change order work.”

As an owner, CFO or operations executive of a subcontracting company, why not eliminate the positive or negative impact changes have on a job cost by separating them? That way, when you call and ask, “Why did we drop two points on the original base contract?” You can be sure the response won’t be, “It’s because of all the change order work.” In other words, if you eliminate the ‘thing’ that distorts a job cost most, you will recognize a problem sooner rather than later. 

KEYWORDS: business management

Share This Story

Looking for a reprint of this article?
From high-res PDFs to custom plaques, order your copy today!

Pete Battisti has been in the commercial drywall business for 20 years.

Recommended Content

JOIN TODAY
To unlock your recommendations.

Already have an account? Sign In

  • Abercrombie & Fitch

    EIFS in 2026: How Specialty Finishes Are Redefining Exterior Wall Systems

    As building codes, owner expectations, and design demands...
    Stucco/EIFS
    By: Regi Mendoza
  • proper air and vapor control

    From Energy Efficiency to Moisture Management: Why Air and Vapor Control Matter

    How proper air and vapor control within building...
    Building Envelope
    By: Benjamin Meyer AIA, LEED AP
  • Linear Metal Ceiling Beam Baffles

    Top 25 Ceiling Contractors of 2026

    Suspended ceilings demand precision, code compliance and...
    Ceilings
    By: John Wyatt and Tanja Kern
You must login or register in order to post a comment.

Report Abusive Comment

Manage My Account
  • eMagazine Subscription
  • Newsletters
  • Online Registration
  • Manage My Preferences
  • Subscription Customer Service

More Videos

Sponsored Content

Sponsored Content is a special paid section where industry companies provide high quality, objective, non-commercial content around topics of interest to the Walls & Ceilings audience. All Sponsored Content is supplied by the advertising company and any opinions expressed in this article are those of the author and not necessarily reflect the views of Walls & Ceilings or its parent company, BNP Media. Interested in participating in our Sponsored Content section? Contact your local rep!

close
  • medical professionals moving a patient on a stretcher through the halls of a medical building
    Sponsored byNational Gypsum Company

    What Does High Performance Mean When It Comes To Gypsum Boards?

Popular Stories

Linear Metal Ceiling Beam Baffles

Top 25 Ceiling Contractors of 2026

Wichita Biomedical Campus

Wichita Drywall Worker Dies After Scaffolding Fall

QXO Just Changed the Game-Here's What Contractors Are Asking

QXO Just Changed the Game-Here's What Contractors Are Asking

An interior drywalling work in progress

Boost Profits with AI Scheduling

Events

June 24, 2026

The Bright Side & Benefits of Designing with Integrated Lighting

Credits 1 AIA LU/HSW; 0.1 ICC CEU

This course will explore the pivotal role architects and lighting design play in creating safer, more sustainable spaces. Learn how to avoid common lighting mistakes and make informed decisions that create the best visual environment for occupants. 

January 1, 2030

Webinar Sponsorship Information

For webinar sponsorship information, visit www.bnpevents.com/webinars or email webinars@bnpmedia.com.

See our full library of webinars

View All Submit An Event

Products

2026 National Painting Cost Estimator

2026 National Painting Cost Estimator

See More Products

Related Articles

  • CS stacked black text 900 x 550.jpg

    Change Order Software for Drywall Contractors

    See More
  • The Truth About Low-Level Lifts

    See More
  • The Truth About Spray-Foam

    See More

Related Products

See More Products
  • M:\General Shared\__AEC Store Katie Z\AEC Store\Images\Walls & Ceilings\new site\Contractors_guide-change-or.gif

    Contractor's Guide to Change Orders

See More Products

Related Directories

  • The QUIKRETE Companies

    Concrete and mortar mixes, cements; concrete repair products, stucco, waterproofing, tile setting and blacktop products, floor underlayments and overlayments, sand and aggregates, concrete coatings, shotcrete products, bulk products, and other seasonal items.
×

Connect with the industry’s leading resource for unparalleled insights and education.

Join thousands of industry professionals today. Shouldn’t you know what they know?

JOIN NOW
  • RESOURCES
    • Advertise
    • Contact Us
    • Directories
    • Store
    • Want More
  • SIGN UP TODAY
    • Create Account
    • eMagazine
    • Newsletters
    • Customer Service
    • Manage Preferences
  • SERVICES
    • Marketing Services
    • Reprints
    • Market Research
    • List Rental
    • Survey/Respondent Access
  • STAY CONNECTED
    • LinkedIn
    • Facebook
    • Instagram
    • YouTube
    • X
  • PRIVACY
    • PRIVACY POLICY
    • TERMS & CONDITIONS
    • DO NOT SELL MY PERSONAL INFORMATION
    • PRIVACY REQUEST
    • ACCESSIBILITY

Copyright ©2026. All Rights Reserved BNP Media, Inc. and BNP Media II, LLC.

Design, CMS, Hosting & Web Development :: ePublishing